Reference Resources

Official lookup links and reference documents used by the sales and engineering teams: customs declaration exchange rates, Taipower's county-level solar capacity factor data, and the latest feed-in tariff schedule.

01 — Customs Lookup

Ten-Day Customs Exchange Rate / Trade Statistics

Taiwan Customs Administration publishes the applicable foreign-exchange rate for customs declarations three times per month (each ten-day period), used to verify dutiable value on imported equipment and modules. A general import/export trade statistics query system is also available.

02 — Taipower Solar Capacity Factor by County

County-Level Solar Capacity Factor (FY110–114)

Both the FY113 and FY114 original PDFs are archived on this site. FY110–112 are not separately archived by Taipower — for historical data, contact Taipower directly or check their latest announcement page below. The summary table and the FIT Rate Calculator's annual generation-hour estimate both use FY114 data.

FY114 Summary (Sorted High to Low)

County/CityAvg. Capacity Factor (A)
連江縣15.45%
金門縣14.68%
澎湖縣14.26%
彰化縣13.98%
台南市13.77%
台中市13.70%
苗栗縣13.56%
雲林縣13.48%
新竹市13.35%
嘉義縣13.25%
嘉義市13.09%
高雄市13.08%
台東縣12.93%
屏東縣12.60%
新竹縣12.58%
南投縣12.48%
桃園市12.38%
花蓮縣11.94%
台北市11.48%
宜蘭縣11.48%
新北市11.30%
基隆市11.02%
National Average13.21%

Source: Taiwan Power Company, "FY114 County-Level Average Unit Solar Capacity Factor (Full Feed-in)." Covers solar sites selling 100% of output to Taipower, excluding Taipower's own sites, direct/wheeling supply, surplus feed-in, and anomalous-output sites. Capacity factor = total annual purchased energy ÷ (installed capacity × billing days × 24 hours). Actual site output varies with commissioning date, equipment efficiency, and local irradiance.

03 — Feed-in Tariff Schedule

FY115 Solar Feed-in Tariff Schedule

Due to the "three PV environmental-review laws," FY115 solar tariffs carry over FY114 H2 rates for the full year — Period 1 and Period 2 are identical. Contract terms lock in for 20 years at the rate announced in the year of signing.

CategoryCapacity TierRate (NT$/kWh)
Rooftop1 kW+ to under 10 kW5.6279
10 kW+ to under 20 kW5.3819
20 kW+ to under 50 kW4.2505
50 kW+ to under 100 kW4.0459
100 kW+ to under 500 kW3.7152
500 kW+3.6236
Ground-MountNo tiering3.5037
FloatingNo tiering3.8948

Additional bonuses may apply: regional bonus (outlying islands / Keelung, Taipei, New Taipei, Taoyuan, Hsinchu County & City, Miaoli, Yilan, Hualien +15%; Taitung +8%), "Green Roof for All" program (+3%, rooftop only), and all-VPC-certified modules (exact lookup by mount type and capacity tier per Schedule 4, not an approximation); a module recycling fee (per Schedule 4, NT$0.0656/kWh, flat rate for rooftop/ground-mount/floating) is added on top. Ground-mount sites may also incur a grid reinforcement fee per Schedule 6 (NT$0.1356/kWh distribution level or NT$0.0866/kWh transmission level, as assessed by Taipower case-by-case). Use the FIT Rate Calculator below for a full computation.

Go to FIT Rate Calculator →

Source: Taiwan Energy Administration, "FY115 Renewable Energy Feed-in Tariff and Formula" (announced 2026-01-02, Doc. No. 經能字第11458005630號). The official announcement governs in case of discrepancy.